ERDF LCCI building renovation and restoration

On june 30, 2015 the reconstruction and restoration works of the LCCI building have been completed.

Project results:

  • renovated 1st floor staircase, lobby - hall, stairs to 2nd floor and basement
  • reconstructed internal power supply networks
  • restored interior elements  - mirror frame, doors, stairs, ceiling and wall decors.

Construction completion time: 4 months (construction started on 02.03.2015).

Total construction costs: 99 983.95 EUR.

ERDF co-financing (48.05%): 49 997.86 EUR.