On june 30, 2015 the reconstruction and restoration works of the LCCI building have been completed.
Project results:
- renovated 1st floor staircase, lobby - hall, stairs to 2nd floor and basement
- reconstructed internal power supply networks
- restored interior elements - mirror frame, doors, stairs, ceiling and wall decors.
Construction completion time: 4 months (construction started on 02.03.2015).
Total construction costs: 99 983.95 EUR.
ERDF co-financing (48.05%): 49 997.86 EUR.